Opening of the Poutès dam on Monday 7 October

As has been the case every year for the past 3 years, the large gates of the ‘New Poutès’ were opened in automn to allow the highly migratory fish free passage and a free access to the best spawning grounds.

This year, 67 salmon from the Loire-Allier axis passed through the fish pass on the right bank of the Vichy dam bridge, but it is estimated that around a hundred fish must have passed through.

After interrupting their migration to spend the summer between Vichy and Langeac in the Allier or its tributaries, the survivors have restarted their migration towards the Dore, Sioule or Alagnon, and of course the Allier, with the arrival of more favourable temperatures. Over the next few days, they will pass through the Brioude, Vielle Brioude and Langeac dams before reaching the new Poutès dam, where the sluice gates were lowered on Monday in anticipation of their arrival.

Last year, spawning grounds were observed upstream of the Poutès, indicating that more than a dozen fish had returned to the Upper Allier. It is not yet possible to count fish at Poutès when the gates are open, but observing the spawning grounds upstream is still a good indicator. About ten spawners are expected to pass this year.

The gates will remain open for 2 months before closing again to enable hydroelectric production to resume.

 

Watch our two 2-minute videos

 

and the webpage : ‘New Poutes dam‘

World Migratory Fish Day: Watch and share our videos

To mark World Migratory Fish Day on Saturday 25 May, ERN-SOS Loire Vivante is launching three videos about Atlantic salmon and ecological continuity.

These videos are previews of remixed extracts from the documentary entitled “Pour une fois qu’il faut laisser couler”, which will be released shortly.

The 2-minute portrait and landscape modules presented here, in French and English, plunge you into the life of the Atlantic salmon in the Allier and Sélune rivers and present 2 major innovative and far-reaching actions that France has taken to restore access to the upstream areas of rivers and streams, the historic breeding grounds of the Atlantic salmon.

Discover these videos :

The New Poutès, the dam that opens for wild salmon 
watch the French version / watch the English version

Allier River : An obstacle course for salmon
watch the French version / watch the English version

France: The largest dam removal project in the world, 2017-2022
watch the French version / watch the English version

 

All the videos can also be viewed on our new YouTube channel: “Rivières Vivantes – Laisser Couler”: https://www.youtube.com/channel/UCjokCmOpXMcgD4ag3UY3ctg

Note :

  • France is the European leader in the restoration of ecological continuity, particularly through the removal of small and large transverse structures. Since 1997, it has built up recognised expertise through innovative policies and major international projects. At a time when the decline in populations of migratory fish and fish at the head of river basins, such as trout, is alarming, we need to pursue innovative actions that provide the most effective response to the challenges of biodiversity.
  • To publicise France’s experience, you will soon be able to watch the full documentary produced by ERN – SOS Loire Vivante as part of the OFB’s Mobbiodiv call for projects. The 3-part film, told from the point of view of our association, traces the history of the major events and projects that have marked the restoration of free movement of rivers in France from 1997 to the present day.
    “For once it’s time to let things flow
    part 1/3: Reopening river routes to large migratory species
    part 2/3: Reconnecting small and medium-sized rivers
    part 3/3: Rethinking and reconfiguring major blocking structures

Poutès Dam on the Allier river : Deconstruction ongoing !

Remember, at the end of August 2019 the 3 sluice gates of the Poutès dam had been removed. This year the work program becomes even more interesting! The construction site was re-installed at the end of May and since July 1st you can see the machines attacking the civil engineering of the dam !

Weir partial removal on the right bank – July 2020 © EDF

This year, the 3 weirs and the 2 piers will be lowered and the footbridge removed. A notch on the left bank will be created and will allow the circulation of water, fish and sediments without hindrance until the summer of 2021 ! The devices for upstream and downstream migration will start to be modified to correspond to the new coasts and standards of the dam (digging under the elevator in particular).

All the details in the video below

The Allier has already recovered its natural profile, as shown by the photo taken in the old reservoir after the emptying.

Upstream of the Poutès dam (inside old reservoir), 11th of June, the Allier regains its natural character for ever © SOS Loire Vivante – ERN

On the 12 of June, a major flood occurred on the Allier (400m3/s at Poutès against 16m 3/s for the module), it crossed the dam without constraint. The warning systems of the Cristal network were effective. The works were suspended and the platform created to work at the foot of the Poutès dam could be evacuated in time without affecting the equipment or the men!

The June 12 flood passes the Poutes dam without constraint © EDF

More info on Poutes dedicated page

New Poutès : the three sluices will be removed at the end of this summer

The work for the new Poutès in the upper part of the Allier basin (France) is ongoing. And we will soon have an important momentum in the history of the Poutès dam. Indeed, at the end of the summer, the three sluices, each 14x5m and 20 tons, will be removed from the structure.

Since the end of May, the reservoir is completely emptied, revealing the old bed of the Allier river.

The bottom sluice gate is fully open. The machines will soon invest the area. A platform that will remain until 2021 (expected end of works) will be installed in front of the dam to allow work on the structure. A crane will then take the sluice, put them on the platform, where they will be cut before joining a revaluation workshop. The reservoir will be refill during the winter 2019. The removal of a part of the dam itself will then continue during spring of 2020 after the smolts downstream migration.

See schedule for work until 2021, and the history of Poutès dam in our dedicated webpage

Reminder, the Poutès dam will be lowered by 10 meters (now it is 17m) and completely retrofit to facilitate fish migration and sediment transport.

© Louis Sauvadet – APS – 31 mai 2019

Partial dam removal of the Poutès dam : Last local public consultation open

for more information visite the official site of the consultation process (ends 28 december 2018) , in french only

> Consultation “dossier d’enquête publique”, in french only
> Read our french press release 

> more information on the project (in english)

Partial dam removal of the Poutès dam : Last local public consultation open

for more information visite the official site of the consultation process (ends 28 december 2018) , in french only

> Consultation “dossier d’enquête publique”, in french only
> Read our french press release 

> more information on the project (in english)

Poutès dam (France) : the demolition and the reconfiguration process starts in june 2017

Please read our Pressrelease 10.022017 .- in french more information on the Poutès dam  

© 2016-2026 Tous droits réservés | European Rivers Network