Sélune: the work on the Vezins dam is coming to an end!

Since March, and in view of the health crisis, the Vezins works carried out by the DDTM 50 has been at a standstill. Only the central pier and the foundations remain today. With some delay, the work will resume until September so that the Sélune can finally be reopened. On the La Roche-qui-boit dam downstream, the only one remaining to date, EDF, the project manager for the site, will launch the sediment management work in June 2020. The final emptying of the reservoir is scheduled for April 2021 and the deconstruction of the dam at the end of 2021-early 2022.

>> More info on our dedicated pages